F.B. Choppy (Pty) Ltd v NSJ Construction Pty. Ltd. & Anor (CS 27/2010 and CS 29/2020) [2019] SCSC 297 (07 April 2019);

IN THE SUPREMECOURT OF SEYCHELLES

 

 Reportable

[2019] SCSC 297

CS 27/2010

CS 29/2010

 

 

 

F.B CHOPPY (PROPRIETARY) LIMITED                    Plaintiff

(rep by Elvis Chetty)

 

and

 

NSJ CONSTRUCTION PTY. LTD.                                   1stDefendant

 

And

GREGOIRE PAYET                                                            2nd Defendant

Marchesseau v Euodoo (Pty) Limited (CS43/2019) [2019] SCSC 852 (03 October 2019);

search_summary: 

Breach of contract of contrat d’entreprise rescission - damages

TWOMEY CJ

The Pleadings

[1]        In a Plaint entered in March 2019, the Plaintiff averred that he had entered into a contract with the Defendant in November 2017 in which the Defendant had agreed to construct a vertical extension to her home in consideration of the sum of SR1, 300,000 with the works to be completed in approximately five and a half months.